Interstate 55 widening project from Route M to Route Z

Interstate 55 at looking south with the new third lane.
This project will add a lane in each direction on I-55. The project is funded by American Recovery and Reinvestment Act (ARRA).

The project also includes new bridges on I-55 over Route M. A soundwall study will also be
performed on I-55 from Route M to Route Z.
Construction began in March 2010.

The Project includes:
Construction begins in March 2010 through 2012. Construction work will address the congestion problem by widening the interstate to 3 lanes in each direction and will address the safety issues by adding features such as median shoulders, new high friction pavement, and high tension guard cable. The project construction cost is approximately $ 15-20 million and was funded by the American Recovery and Reinvestment Act.

Construction Schedule and Impacts:
-
During the construction of the bridges over Route M and Glaize Creek, the lanes of traffic will be shifted, the speed reduced (70 mph to 50 mph) and the lane widths reduced to 11 foot lanes over Route M.
Noise analysis to be performed
A noise analysis is required whenever MoDOT widens an existing roadway. MoDOT will use a federally approved traffic model to analyze the change in noise from the widened I-55 from Route M to Route Z. The model looks at a 20-year noise projection. Noise levels must be projected at greater than 66 decibels to require construction of noise abatement, which is typically a soundwall. For more information on MoDOT’s soundwall policy, please click on:
http://www.modot.mo.gov/stlouis/links/docs/sndwalls_304.pdf