News Release Aug. 12, 2011 - MoDOT Provides Update on South Lincoln Drive Project
A public hearing was held on Thursday, October 14, 2010 about the proposed design of the interchange. More than 70 people attended and about a dozen shared comments, both online and through mail/comment box. Nearly every comment supported the design; however, there were a few who were concerned about roundabouts and the ability to fit large vehicles safely through them. Since the public hearing, several other meetings have been held with those concerned, and while minor changes are being made to the design, MoDOT expects to take this design to its Commission for approval this winter.
TIMELINE:
- Right of way appraisal and negotiation to begin
in Spring 2011
- Project awarded to contractor in Spring 2012
- Construction begins in Summer 2012
- Interchange opens in Fall 2013 |
FACTS:
- Estimated cost $10 million
- Includes three roundabouts
- Completes east outer road connecting Route C
- To be located north of existing S. Lincoln Drive intersection at US 61
- Includes removal of existing connections at S. Lincoln Drive and Bueneman Lane
|
|