Route: Rt. DD at McAdoo Creek
Bridge No.: A0749
Construction Start: Mar. 7, 2011
Days closed: 53
Contractor: KTU Constructors
Detour: Map
Status: OPEN
Daily traffic volume: 5,434
Route: Rt. DD at Clear Creek
Bridge No.: A0750
Construction Start: Mar. 7, 2011
Days closed: 53
Contractor: KTU Constructors
Detour: Map
Status: OPEN
Daily traffic volume: 5,434
Route: Rt. CC at Flagstaff Creek
Bridge No.: A1890
Construction Start: March 2011
Days closed: 35
Contractor: KTU Constructors
Detour:
Status: OPEN
Daily traffic volume: 283
Route: Rt. PP at Clear Creek
Bridge No.: N0361
Construction Start: Early June 2011
Days closed:53
Contractor: KTU Constructors
Detour: No detour will be posted
Status: OPEN
Daily traffic volume: 350
Route: U.S. 50 at Butcher's Creek
Bridge No.: G0953
Construction Start: April 11, 2011
Days closed: 52
Contractor: KTU Constructors
Detour: Map
Status: OPEN
Daily traffic volume: 6,501
Route: Mo. 58 at Union Pacific Railroad
Bridge No.: K0429
Construction Start: Summer 2012
Days closed: 53
Contractor:KTU Constructors
Detour: Map
Status: Currently in design
Daily traffic volume: 2,643
Route: Mo. 2 at Big Creek
Bridge No.: L0142
Construction Start: June 20, 2011
Days closed: 53
Contractor: KTU Constructors
Detour: Map
Status:OPEN
Daily traffic volume: 880
Route: Rt. BB at Post Oak Creek
Bridge No.: N0111
Construction Start: May 2011
Days closed: 53
Contractor: KTU Constructors
Detour: Map
Status: OPEN
Daily traffic volume: 1,184
Route: Rt. CC at Peavine Creek
Bridge No.: R0472
Construction Start: May 2011
Days closed: 53
Contractor: KTU Constructors
Detour: No detour will be posted
Status: OPEN
Daily traffic volume: 283
Route: Rt. E at Black Jack Creek
Bridge No.: T0818
Construction Start: Summer 2011
Days closed: 35
Contractor: APAC
Detour:
Status: OPEN
Daily traffic volume: 283
Route: Rt. E at Walnut Creek
Bridge No.: X0855
Construction Start: April 2011
Days closed: 49
Contractor: KTU Constructors
Detour: Map
Status: OPEN
Daily traffic volume: 758
Route: Rt. B at Big Creek
Bridge No.: N0963
Construction Start: August 2011
Days closed: 102
Contractor: Leath & Sons
Detour: Map
Status: OPEN
Daily traffic volume: 793
|