Route: Mo. 92 East at First Creek
Bridge No.: J0923
Construction Start: Spring 2012
Days closed:
Contractor:
Detour: Map
Status:
Daily traffic volume: 5,598
Route: U.S. 69 BNSF Railroad Bridge
Bridge No.: K0140
Construction Start: Winter 2011
Days closed: 47
Contractor:
Detour: Map
Status:
Daily traffic volume: 11,181
Route: U.S. 69 BNSF Railroad Bridge
Bridge No.: L0502
Construction Start: Summer 2012
Days closed:
Contractor:
Detour: Map
Status:
Daily traffic volume: 371
|