Construction VE
Beginning in late 1989 (Federal Fiscal Year 1990) the department
added a construction value engineering program. Contractors
submit Value Engineering Change Proposals (VECP'S) for department review and
approval.
If accepted, the contractor and the department
share the total savings on a 50/50 basis. Beginning in 2007, contractors can submit Practical Design Value Engineering Change Proposal (PDVECP).
If accepted, PDVECP savings are split 25% Contractor/75%. MoDOT PDVECP typically consist of an existing feature that could remain a part of the final project, for example, exisiting pavement, an existing pipe, etc. See file below for a summary of the Federal Fiscal Year 2007 Construction VECP's and PDVECP's.
VECP's by Engineering Policy Guide Categories
200 Geometric
300 Bases
400 Flexible Pavement
500 Rigid Pavement
600 Incidental Construction
700 Structures and Hydraulics
800 Roadside Development
900 Traffic Control
1000 Materials
1100 Maintenance Materials
Other documents:
For any questions or to request a VE study, contact ValueEng@modot.mo.gov
The documents are provided in Acrobat Reader format. Free Acrobat Reader download  |